Sixth Stakeholder Meeting
Wednesday March 12, 2003
The Cape Codder Resort (Crystal Ballroom, Downstairs)
Route 132 & Bearses Way, 1225 Iyanough Road
Hyannis, MA 02601
Alternative Sites Analysis
Facilitators: Dr. Jonathan Raab, Raab Associates, Ltd with Suzanne Orenstein
Agenda
9:00 Preliminary Screening of Alternative Sites
Lt. Col. Brian A. Green, Deputy District Engineer, Army Corps of Engineers
- Opening Remarks
Karen Adams, Chief Permits & Enforcement Branch, Army Corps of Engineers
- Selection Criteria
- Sites Under Consideration
10:15 Break
10:30 Preliminary Screening of Alternative Sites (continued)
Karen Adams, Chief Permits & Enforcement Branch, Army Corps of Engineers
- Information Collected on Each Site
- Schedule Implications
11:45 Wrap-Up / Next Steps
12:00 Adjourn
Note: We intend to allow clarifying questions and comments after each of the four sub-topics in Karen Adams presentation. As usual we will begin with the Stakeholder members and then move to the Resources, and then to the public if there is sufficient time.
Please also note, that in addition to Karen Adams, the Corps will have the following individuals at the meeting:
Christine Godfrey, Chief, Regulatory Division, Army Corps of Engineers
Larry Rosenberg, Chief, Public Affairs, Army Corps of Engineers
Leo Roy, The Bioengineering Group